| The  Stoltz Exploratory Plan for the Barley   Mill Plaza  site has been found unacceptable by our New Castle County Land  Use Department professional planners.  I have appended the County Land Use  Department’s 7/8/08 letter below.  The  County Land Use Department letter states in part: “Upon completion and  incorporation of the Exploratory Comments (June 19, 2008), you may submit a  revised Exploratory Plan and appropriate fees to the Department of Land  Use for review.”  Please carefully review the earlier June 19, 2008  referenced letter and other relevant documents at www.bobweiner.com.  The  County’s rejection was based upon issues raised by our community at the July 1  Planning Board/Land Use Department Hearing, included compatibility with  community scale and character, traffic related issues, drainage, noise and  lighting.  Acting General Manager George   Haggerty was very complimentary of Greenville citizens who testified noting that  our comments were, for the most part, relevant and within the context of the  applicable rules and regulations.  However,  please be advised that the Stoltz organization will submit a new plan which may  not be significantly distinguishable from the plan just found to be  unacceptable. [Alternatively, the Stoltz organization could opt to challenge  the regulatory ruling at this juncture or at a later time.]  While  I am proud of our collective efforts, I must admonish everyone that we must  remain constantly vigilant. I will continue to keep you apprised of all  relevant actions. I promise to provide you with guidance and direction.  Best  wishes.   Bob  Weiner, your County   Councilman“Making  County Government Work for Us”
 Robert  S. Weiner
 Council  District 2, New Castle County,   DE
 www.bobweiner.com
 Louis  Hinkle, aide to Councilman Weiner 302-395-8362
 July 8, 2008  Mr. Jim Lober Apex Engineering, Inc.
 27 West Market Street
 Newport, DE 19804
 RE:  Barley Mill   Plaza – Application  Number 2008-0275-S Dear Mr. Lober: I am writing to you in reference to  your Exploratory Plan submittal that is titled Barley Mill   Plaza to the Department  of Land Use and the Planning Board for review and comment.  As you are  aware, this plan was furthered reviewed at the July 1, 2008 Planning Board  Public Hearing. As you are aware, issues raised at  the hearing included compatibility with community scale and character, traffic  related issues, drainage, noise and lighting.  The applicant should be  prepared to respond to code compliance related issues as the plan proceeds  through the review process.    Please note that the Exploratory  Plan has been found unacceptable.  At this time these are the final  comments of the Department of Land Use.  Upon completion and incorporation  of the Exploratory Comments (June 19, 2008), you may submit a revised Exploratory  Plan and appropriate fees to the Department of Land Use for review.   Please note that your application  number for this project will remain 2008-02752-S.  If you wish to discuss  these matters further, please contact me at 87 Reads Way, Corporate Commons, New Castle, DE   19720, or call me at 302-395-5414.   Thank you for your continued cooperation during this process. Sincerely,   Antoni I. SekowskiPlanner III
 CC:  Steve LewisMichael J. Bennett
 David M. Culver
 file
 |